Bio Methane PRS Installation

iGAS Commission Bio Methane PRS Installation

iGAS have completed another successful Bio Methane PRS installation, which was commissioned within two days of delivery on site.

  • Despatched Thursday 16th March
  • Arrived on site Monday 20th March
  • Connected to client services & engine Tuesday 21st March (am)
  • System run at full load (5Mw / 1000 Nm3/hr Bio Methane) Tuesday 21st March (pm)

Another happy customer and a great example of how factory acceptance testing of modules prior to despatch leads to a fast and successful commissioning of the client installation.

Bio Methane PRS Installation

Another Bio Methane PRS Installation Commissioned